Factors for Delay in LRT Bridge Structure Work
DOI:
https://doi.org/10.31695/IJERAT.2019.3541Keywords:
LRT, Delay Time, Bridge Structure, RIIAbstract
In order to increase economic growth through infrastructure development in Indonesia, the Government accelerates projects that are considered strategic and have high urgency to be realized in a short period of time. The construction of the Jabodebek LRT project has taken almost four years since 2015. The government has targeted the project to be completed in April 2019, but the realization has been delayed, which is only around 50%. For this reason, the researcher wants to discuss the factors that delay the construction work of the LRT bridge structure. The following results from data processing using RII analysis: 1. Weak planning
and project scheduling by contractors, 2. Project time optimization, 3. Ineffective planning and scheduling, 4. Determination of duration, 5. Contractors who lack experience, 6. Weak communication and coordination by service users during construction, 7. Different surface conditions of subsoil, 8. Solid traffic, crowds and other disturbances in the field, 9. Low quality of project control and 10. Lack of control. It is expected that from the results of the above data analysis it can contribute to the construction world, especially the construction of the LRT project
Downloads
Published
Issue
Section
License
Copyright (c) 2019 Maulana Abidin, Nunung Widyaningsih, Bambang Purwoko Kusumo Bintoro
This work is licensed under a Creative Commons Attribution 4.0 International License.