Productivity Analysis f Performance Measurement by (Earned Value Management) EVM in High-Level Building Projects

Authors

  • Dirga Oktrianto Mercu Buana University Jakarta Indonesia
  • Budi Susetyo Mercu Buana University Jakarta Indonesia

DOI:

https://doi.org/10.31695/IJERAT.2020.3624

Keywords:

EVM Method, Scheduling, Construction Project

Abstract

Project scheduling helps show the relationship of each activity to other activities and to the entire project, identifies relationships that should take precedence between activities, and shows a realistic estimated time for each activity. EVM (Earned Value Management) is one of the measurement methods to objectively measure project performance and progress. This method can integrate time and cost so that it can know whether a project is running faster or slower than the schedule that is supposed to and to know whether the project costs are greater or smaller than they should have planned. The steps in the EVM calculation are included in the control process in which the steps are carried out such as calculations, analysis, forecasting, cost reporting and schedule performance for project stakeholder evaluations and actions. This study aims to calculate, analyze and measure the performance of the Wisma Atlet Kemayoran-Central Jakarta project schedule using the EVM method. With the EVM method, it is expected that the costs and time for the project can be controlled so that the project can be completed on time and the costs incurred according to the project budget.

References

Subandiyah Azis et al, ‘ Optimization of Rescheduling and Economy Analysis of the Implementation of Kwitang Office Park Building Construction Project in Jakarta’, Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317 – 333

S.M.B.Jaswanth et al, OPTIMIZATION OF PLANNING, SCHEDULING, AND CONTROL OF HIGH RISE CONSTRUCTION PROJECTS, International Journal of Civil Engineering and Technology (IJCIET), Volume 9, Issue 4, April 2018

Wallace Agyei, Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming: Case Study, INTERNATIONAL JOURNAL OF SCIENTIFIC & TECHNOLOGY RESEARCH, VOLUME 4, ISSUE 08, AUGUST 2015

Rama.S et al , A Study on Project Planning Using the Deterministic and Probabilistic Models by Network Scheduling Techniques, Int. Journal of Engineering Research and Application, Vol. 7, Issue 3, ( Part -4) March 2017

de Souza, A. D., et. al. , 2015. A Proposal for the Improvement of Project s Cost Predictability Using Earned Value Management and Historical Data of Cost An Empirical Study. International Journal of Software Engineering and Knowledge Engineering.

Khesal, T., et. al. 2018. Integrated cost, quality, risk and schedule control through Earned Value Management ( EVM ). Journal of Engineering, Design and Technology. https://doi.org/10.1108/JEDT-07-2018-0119

Yoga Tryas Pratama & Budi Susetyo, 2019. Cost Analysis of Facade Work in High-Rise Building by Value, International Journal of Engineering Research and Advanced Technology (IJERAT), Volume 5.

Padhye, S.L. (2000). Implementation: A Problem For Value Management Pratitioner. SAVE International Confrence Proceeding

Adi Lukman Amir & Budi Susetyo, 2019. EVALUATION OF COST AND TIME USING EARNED VALUE METHOD (EVM) AND STRUCTURAL EQUATION MODELING (SEM) IN PARKING BUILDING PROJECTS, https://repository.mercubuana.ac.id/view/divisions/557/2019.default.html

Downloads

Published

2020-07-20

Issue

Section

Articles

How to Cite

Productivity Analysis f Performance Measurement by (Earned Value Management) EVM in High-Level Building Projects . (2020). International Journal of Engineering Research and Advanced Technology (ijerat) (E-ISSN 2454-6135) , 6(7), 18-26. https://doi.org/10.31695/IJERAT.2020.3624